1. |
29-Feb-2024 06:30 PM |
26-Apr-2024 12:30 PM |
29-Apr-2024 03:30 PM |
[Procurement of 220kV Solid Core Insulators]
[TR-13/2024][2024_MPPTC_339680_1]
|
MP Power Transmission Co. Ltd.||MPPTCL.CE(Procurement)
|
2. |
14-Mar-2024 05:30 PM |
26-Apr-2024 12:30 PM |
30-Apr-2024 03:30 PM |
[Procurement of 400 kV, 2000 A, three phase (separate R,Y,B Phase) Pantograph Isolator with earth switch complete with structure and support insulators]
[TR-24/2024][2024_MPPTC_345418_1]
|
MP Power Transmission Co. Ltd.||MPPTCL.CE(Procurement)
|
3. |
26-Feb-2024 06:55 PM |
26-Apr-2024 03:00 PM |
30-Apr-2024 03:30 PM |
[Work contract for routine maintenance and operational work of Dam filling pumps (Including overhauling of Pumps) at ATPS, MPPGCL, Chachai]
[2169][2024_MPPGC_329200_1]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Amarkantak Thermal Power Station-Chachai - MPPGCL
|
4. |
15-Mar-2024 06:00 PM |
26-Apr-2024 03:00 PM |
29-Apr-2024 03:30 PM |
[Procurement of water mist/ fog cannon dust suppression system for track Hopper of CHP-210 MW ATPS MPPGCL Chachai.]
[2617][2024_MPPGC_345076_1]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Amarkantak Thermal Power Station-Chachai - MPPGCL
|
5. |
15-Mar-2024 06:55 PM |
26-Apr-2024 03:00 PM |
30-Apr-2024 03:30 PM |
[Complete repairing/ replacement and testing of 630 kVA defective transformer at new ash dam of 500MW unit, at SGTPS, MPPGCL, Birsinghpur.]
[322758][2023_MPPGC_322758_2]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Sanjay Gandhi Thermal Power Station-Birsinghpur - MPPGCL
|
6. |
26-Feb-2024 06:55 PM |
26-Apr-2024 03:00 PM |
30-Apr-2024 03:30 PM |
[Work contract for Availing Expert Supervisory services for the overhauling of FD fans type FAF 17/9.5 1 installed at the boiler of 1x210 MW unit, ATPS, MPPGCL, Chachai]
[2253][2024_MPPGC_331455_1]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Amarkantak Thermal Power Station-Chachai - MPPGCL
|
7. |
15-Mar-2024 05:30 PM |
26-Apr-2024 03:00 PM |
30-Apr-2024 04:00 PM |
[Hiring of one number Water Mist Fog Machine Water Mist Sprayer Fogger for Ash Silo of PH-IV, STPS, MPPGCL, Sarni along with O N M services]
[WT4580][2024_MPPGC_345892_1]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Satpura Thermal Power Station-Sarni - MPPGCL
|
8. |
14-Mar-2024 06:55 PM |
26-Apr-2024 03:00 PM |
29-Apr-2024 03:30 PM |
[Procurement of Scale inhibitor, Organo Phospho-nate-HEDP based formulation for cooling water treatment system 210 MW ATPS MPPGCL Chachai.]
[164][2024_MPPGC_345098_1]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Amarkantak Thermal Power Station-Chachai - MPPGCL
|
9. |
06-Mar-2024 11:00 AM |
26-Apr-2024 03:00 PM |
30-Apr-2024 03:30 PM |
[Procurement of Gear Box for 8.5 E 9 Coal Mill installed at Unit No 1 to 4 of PH I and II SGTPS MPPGCL Birsinghpur]
[338301][2024_MPPGC_338301_1]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Sanjay Gandhi Thermal Power Station-Birsinghpur - MPPGCL
|
10. |
07-Mar-2024 06:45 PM |
26-Apr-2024 03:00 PM |
30-Apr-2024 03:30 PM |
[Procurement of Collecting Electrode for ESP installed at unit no 1 and 2 2 x 210 Mw of PH I at SGTPS MPPGCL Birsinghpur]
[318335][2023_MPPGC_318335_2]
|
Madhya Pradesh Power Generating Company Limited||Chief Engineer(Gen.)-Sanjay Gandhi Thermal Power Station-Birsinghpur - MPPGCL
|